這是我在公司常用的一個(gè)IE改善工具,現(xiàn)分享給大家。
改善步驟(IMPROVEMENT STEPS)
1. 請(qǐng)資材部提供最近兩個(gè)月的欲生產(chǎn)產(chǎn)品計(jì)劃 ( Take the forecast schedule bbbb PC (2 months) and compare with Production schedule)
-確定量大的產(chǎn)品(Sort high models in the schedule)
2. 制定IE改善計(jì)劃(Make IE improvement schedule )
-從生產(chǎn)排程中挑選量大、成本高的產(chǎn)品進(jìn)行改善 (Select models to high order & cost from forecast schedule for improvement)
-改善的五個(gè)步驟(5 steps for improvement)
1觀測(cè)(Observation)
2分析,BF&AF表單填寫(xiě)(Analyze , Before & After sheet) 3改善(Implement)
4改善效果追蹤(Follow up)
5標(biāo)準(zhǔn)工時(shí)與作業(yè)指導(dǎo)書(shū)的修訂(update Std time)
3. 觀測(cè)流水線作業(yè)時(shí)間(Observation time in production line)
-每個(gè)工序測(cè)5個(gè)時(shí)間(Observe 5 times/Process)
-包含損失的時(shí)間(Not include lost time in observe time (C/T))
4.BF&AF表的制作( Before & After sheet)
這里分3個(gè)部分(There are 3 parts)
1.BF&AF表( Before & After)
-比較改善前(IE工時(shí)、觀測(cè)時(shí)間)和改善后(計(jì)劃改善工時(shí)、實(shí)際改善工時(shí))
(Comparison between Before (IE,Observation)and After (Plan,Actual))
2. 關(guān)鍵指標(biāo)匯總表(Summary)
-最大循環(huán)時(shí)間(C/T)
-生產(chǎn)線平衡率(Line balance efficiency)
-產(chǎn)出數(shù)量(Output)
-標(biāo)準(zhǔn)工時(shí)(Std time)
3. 繪制圖表(Graph)
5. 改善匯總Summary improvement
所有改進(jìn)后的產(chǎn)品關(guān)鍵數(shù)據(jù)匯總表(Summary all models after implement already)
-標(biāo)準(zhǔn)工時(shí)(Std time)
-生產(chǎn)線平衡率(Line balance efficiency)
-產(chǎn)出數(shù)量(Output)
-人力(Man power)
6. 修訂標(biāo)準(zhǔn)工時(shí)表(Update Std time sheet)
沈經(jīng)理 【求購(gòu)】 風(fēng)機(jī) 2025-7-4
李 【求購(gòu)】 配電箱 2025-7-4
李經(jīng)理 【求購(gòu)】 電機(jī)散熱風(fēng)... 2025-7-4
董 【求購(gòu)】 工業(yè)空調(diào) 2025-7-4
張經(jīng)理 【求購(gòu)】 閥門連接器 2025-7-3
沙經(jīng)理 【求購(gòu)】 玻璃破碎報(bào)... 2025-7-3
李旨軍 【求購(gòu)】 定量取樣器 2025-7-3